Challenges
Proceed to the standard exchange of a "main component" by limiting the downtime of the wind turbine.
Challenges to be taken up
- Lifting using a 350T crane at a height of 80m.
- Duration of intervention reduced to a minimum.
- Critical component.
Interventions
- Uncoupling.
- Removal of the roof.
- Standard exchange of generator and air / air exchanger.
- Refitting the roof.
- Re-coupling.
- Lineage.