Challenges

Proceed to the standard exchange of a "main component" by limiting the downtime of the wind turbine.

Challenges to be taken up

  • Lifting using a 350T crane at a height of 80m.
  • Duration of intervention reduced to a minimum.
  • Critical component.

Interventions

  • Uncoupling.
  • Removal of the roof.
  • Standard exchange of generator and air / air exchanger.
  • Refitting the roof.
  • Re-coupling.
  • Lineage.